As part of their strategic plan to reduce time to market for new products and increase product quality, Briggs & Stratton needed to upgrade their acoustic and vibration test lab. Their goals included consolidating lab spaces to bring team members together and increase testing capacity, updating and adding measurement and analysis capabilities, and improving energy efficiency through mechanical and electrical upgrades. ACS was contracted for the design, construction management and commissioning of the 13,500 SF renovation.
ACS designed and built an entirely new roof structure to accommodate the new hemi anechoic chamber. With careful coordination, the roof of the building was removed, and new elevated roof structure was installed. The new roof section also provided support for the air handling units that were supplying the temperature sensitive test spaces.
To access the area and install equipment during the renovation, ACS brought in a helicopter to do the heavy lifting, saving time and money by avoiding the need for an oversized and costly crane.
New test lab location was in the middle of the manufacturing facility footprint, requiring coordination of schedule and contractors.
NVH (Noise Vibration Harshness) testing has very specific requirements for square footage and height of the test space to simulate real world environment in which the product will be used. The roof of the building was opened and removed, and the new elevated roof structure was installed.
Work was sequenced to allow the move of some equipment into renovated space as it was completed.
The work was completed with no disruption to ongoing operations within the facility.